INDUSTRY : Commercial
TYPE : Office Tower
SIZE : 400,000 s.f.
STOREY : 16
BUDGET : $750,000
We were contracted based on our Value Engineering input, not our bid price, a decisiĆ³n which was not necessarily cleared with the design team. Consequently our shop drawings and product data were exposed to a series of rejections.
In order to meet project schedule, we commenced installation , while working diligently with the design team to appease all fronts.
The project was completed on time, and on budget, with our Value Engineering input.